Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Oct 2013 - Mar 2014 |
Australian Government Contribution: | $212,430 |
Local Council/Shire: | Wellington Shire Council |
State: | VIC |
Project DescriptionInspections have revealed significant deterioration of the road pavement, edges of seal constantly breaking away, increasing numbers of potholes, resulting in a reduced service level and high risk, despite prolonged attempts at maintenance patching.
Reconstruct and seal the 2km of road. Works include reshaping of the existing pavement & placement of additional conforming materials. Drainage works as required. Bituminous Sealing 7mm primerseal. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/05/2014