Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Oct 2013 - Nov 2013 |
Australian Government Contribution: | $79,923 |
Local Council/Shire: | Campaspe Shire Council |
State: | VIC |
Project DescriptionExisting bitumen seal reached intervention levels due to severe cracking, poor surface texture and lack of oxidization
Work will be carried out to resurface the pavement with a new layer of bitumen and wearing aggregate (stone)Length 2573m Width 7m |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/02/2014