Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Jan 2014 - Mar 2014 |
Australian Government Contribution: | $244,200 |
Local Council/Shire: | City of Canning |
State: | WA |
Project DescriptionHigh deterioration of road surface due to cracking.
Road rehabilitation utilising foam stabilisation to a depth of 300mm.
Total cost of proposed project is $487,123 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2014