Newcastle Port – Kooragang Island (Tourle Street Bridge Duplication)

Funding Program:Investment Road and Rail Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Mid 2016 - Mid 2018
Estimated Project Cost:$75,952,942
Australian Government Contribution:$37,976,471
Local Council/Shire:Newcastle City Council
State:NSW

Project Description

The project duplicated the Tourle Street Bridge and included approach works at Kooragang Island.

Benefits

The project has improved freight productivity on Tourle Street and Cormorant Road and enhanced the safety and environmental performance of the corridor.

Funding

The Australian and NSW governments funded this project on a 50:50 basis.

Timetable

Construction on the project commenced in June 2016 and was completed in June 2018.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 16/06/2020