Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Mar 2014 - Apr 2014 |
Australian Government Contribution: | $240,546 |
Local Council/Shire: | Greater Shepparton City Council |
State: | VIC |
Project DescriptionSignificant edge breaks and rutting due to inadequate road width. A number of dangerous depressions and seal is stripping
1.6km reconstruction with 8m formation and 6m primer seal using 10mm aggregate. Rip and overlay with 150mm Class 3 crushed rock and install headwalls on existing culverts. Works delivered by Council's internal team. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2014