Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | May 2014 - May 2014 |
Australian Government Contribution: | $27,000 |
Local Council/Shire: | Gilgandra Council |
State: | NSW |
Project DescriptionTimber bridge over the Yarragrin Creek has been replaced with a concrete bridge. The approaches to the new bridge need to be reconstructed, they need to be widened and realigned to suit new structure.
Reform existing approaches (approximately 50m either side of bridge) to align with bridge, widen and lift approach levels to suit new bridge. Win and cart gravel - spread to form approaches - bitumen seal with 14mm stone. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2014