Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Feb 2014 - Jun 2014 |
Australian Government Contribution: | $72,913 |
Local Council/Shire: | Bland Shire Council |
State: | NSW |
Project DescriptionRoad and Gutter deformation.
Start 0 Church St. Finish 209.49 metres down Kurrajong St to Monash St. Work to be located full width of Kurrajong Street @ 0 Church St Intersection & finishing 209.49 metres to Monash St intersection.
Total cost of proposed project is $297,875 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2014