Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Mar 2014 - May 2014 |
Australian Government Contribution: | $90,269 |
State: | NT |
Project DescriptionJump Up is eroded from intensive wet season washouts from storm water runoff.
150 metre by 7.2 metre wide double seal 10 mm and 14 mm aggregate with rate of 1.3 litre per metre of bitumen. A concrete spoon drain install with slow down blocks and relief drainoff install to relieve water flow. Guard railing to be installed on high side of road 100 metres long, with two bull nose ends.
Total cost of proposed project is $142,700 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2014