Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Oct 2014 - May 2015 |
Australian Government Contribution: | $55,205 |
Local Council/Shire: | Shire of Woodanilling |
State: | WA |
Project DescriptionThe gravel on this section of road is seriously deficient as it has been compacted and /or depleted through high usage and lack of maintenance. Trimmer Road is part of a five year gravel sheeting program and this is the last section to be completed
Council propose to prune trees to improve sight distances, clear out blocked culverts, formation work, gravel sheet to 100mm thick by 10m wide to reinstate this section back to original condition. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2015