Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Feb 2015 - Apr 2016 |
Australian Government Contribution: | $570,000 |
Local Council/Shire: | Lake Macquarie City Council |
State: | NSW |
Project DescriptionPoor existing drainage system, unformed road shoulder, narrow road width and poor pavement structure requiring significant improvement to meet the Council's service levels as well as safety for the local residents.
Eastern side of Northville Drive - Construction of approximately 1350 metres of Kerb and Guttering, installation of new drainage system, road widening, and strengthening of the unformed road shoulder.
Western side of Northville Drive - road widening and reconstruction, and construction of approximately 105 metres of Kerb and Guttering on both sides of the road.
Total cost of proposed project is $1,250,000 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2016