Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Nov 2014 - Nov 2014 |
Australian Government Contribution: | $16,000 |
Local Council/Shire: | Indigo Shire Council |
State: | VIC |
Project DescriptionThe road segment was only coated with a single coat bitumen seal and is now deteriorating resulting in holes in the bitumen.
Apply a second coat of bitumen to the road segment for a total length of 1045 metres. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/12/2014