Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Jun 2015 - Dec 2015 |
Australian Government Contribution: | $177,031 |
Local Council/Shire: | Shire of Dandaragan |
State: | WA |
Project DescriptionLoss of stone seal, pavement failure, drainage grate damage and drainage issues.
Reconstruct 265m from Osprey Close to Ward Street intersection with asphalt to also include replacement of damaged kerb, paths and drainage pits. |