Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Nov 2014 - Nov 2014 |
Australian Government Contribution: | $241,941 |
Local Council/Shire: | Gilgandra Council |
State: | NSW |
Project DescriptionMyrtle St, is a well-used town street that was constructed in its present form in the early 60’s. The pavement is continually breaking up and potholing with severe breakouts along the shoulders partly caused by the collapsed/inoperative kerb and gutter. The intersection with Morris St (Eastern end) has caused concerns with its alignment and elevation, a safety issue for both motorists and pedestrians. In councils hierarchical system this street is classed as a primary through street.
Stage 1. Lower the approach to Morris Street intersection by 250mm and re-align Kerb and Gutter .
Stage 2. Rehabilitate pavement full width (12 metres) from the intersection of Morris Street to the intersection of Wamboin Street (350 metres).
Stage 3. Remove old broken/inoperative Kerb and gutter and replace with lay-back style kerb and gutter, Southern side only (350 metres) |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/02/2015