Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Jul 2018 - Jun 2019 |
Australian Government Contribution: | $115,422 |
State: | QLD |
Project DescriptionThe existing creek crossings at Tutu Creek and Little Wachee creek are frequently inundated and impassible for much of the year. Additionally these creek crossing are unsafe with vehicles frequently becoming stuck or damaged.
Upgrade of creek crossings. This includes raising the existing road, construction of causeways and installation of stormwater pipes underneath road to provide improved access
Total cost of proposed project is $202,920 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2019