Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Jan 2016 - Dec 2016 |
Australian Government Contribution: | $129,690 |
State: | SA |
Project DescriptionThe existing road is unsealed and become dusty and corrugated in the summer and slippery after rain events. Dusts generated by traffic linger within the town, causing safety and health issues to the local road users and local residents.
The work will involve reconstructing and sealing of the entire length of Mitchell Street. Mitchell Street is 570 metres long by 7 metres wide. The work will mitigate the dust problem and improve accessibility to properties for local residents. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/02/2017