Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Apr 2015 - Dec 2017 |
Australian Government Contribution: | $265,052 |
Local Council/Shire: | Horsham Rural City Council |
State: | VIC |
Project DescriptionRoad realigned to match newly reconstructed bridge at Norton Creek.
Reconstruction of the pavement to match the bridge profile. This will provide a smooth riding surface, safe traffic passage and improved drainage. Lenghth 470 meters x 6.2 metres wide
Total cost of proposed project is $352,000 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/03/2018