Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Jun 2015 - Jul 2015 |
Australian Government Contribution: | $252,762 |
Local Council/Shire: | Sutherland Shire Council |
State: | NSW |
Project DescriptionRoad pavement is significantly deteriorated due to road wearing surface and base course failure.
Existing wearing surface layer severely oxidised, potholing in patches. Replacement of pavement layer and wearing surface is needed.
Full width road rehabilitation over approximately 4405sq.m. Road pavement works include 200mm thick foam bitumen stabilised base course and 40mm thick asphalt concrete (AC10) wearing surface on top. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/11/2015