Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | May 2015 - Dec 2015 |
Australian Government Contribution: | $75,000 |
Local Council/Shire: | City of Whittlesea |
State: | VIC |
Project DescriptionExtensive cracking in road pavement surface, pavement deformation, worn / damaged shoulders and ineffective table drains.
Repair road pavement by removing 250mm of damaged pavement, stabilise pavement layers, laying replacement asphalt, allowing 6 to 8 weeks to settle then apply an asphalt wearing course and replace line-marking.
Excavate and strengthen shoulders, and re-grade table drain to ensure water flows to stormwater pits.
Total cost of proposed project is $150,000 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/03/2016