Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Feb 2016 - Mar 2016 |
Australian Government Contribution: | $42,982 |
Local Council/Shire: | City of Belmont |
State: | WA |
Project DescriptionExcessive cracking of existing wearing course allowing egress of stormwater runoff into the base course causing pumping of fines to the surface damaging the road structurally.
Length, width and area of the job: 295m x 7.4m = 2,183m2. Profiling of the kerb edges of the asphalt wearing course. Retention of the existing kerbing both sides of the road and adjusting of existing drainage structures to match new road levels. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2016