Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Dec 2015 - Jun 2016 |
Australian Government Contribution: | $47,875 |
Local Council/Shire: | Corporation of the City of Marion |
State: | SA |
Project DescriptionThere are areas of block cracking, water ponding and surface deformation. This is a medium traffic volume road
Edge plane the asphalt 30mm, deep lift the pavement failures, then complete the project with a 30mm AC10 Light Traffic Mix Overlay - 2318 sq m |