Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Dec 2015 - Jun 2016 |
Australian Government Contribution: | $64,848 |
Local Council/Shire: | Corporation of the City of Marion |
State: | SA |
Project DescriptionThere are areas of longitudinal cracking, surface deformation with patches and service trenches. This is a low traffic volume road
Edge plane the asphalt 30mm, then complete the seal with a 30mm AC10 Light Traffic Mix Overlay - 4749 sq m |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/07/2016