Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Sep 2015 - Mar 2016 |
Australian Government Contribution: | $537,900 |
Local Council/Shire: | Sunshine Coast Regional Council |
State: | QLD |
Project DescriptionThe proposed section has the following defects: extensive cracking including fatigue/crocodile craking and longitudinal cracks, deep depressions along the length of the road in the wheel paths. The existing asphalt surface is old, oxidised and brittle. There are major surface failures and moderate pavement failures.
Pavement rehabilitation consisting of in-situ stabilisation of the existing pavement and placement of a new asphalt wearing surface including the installation of subsoil drainage.
Total cost of proposed project is $547,670 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/02/2019