Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Oct 2015 - Feb 2016 |
Australian Government Contribution: | $154,590 |
Local Council/Shire: | Sunshine Coast Regional Council |
State: | QLD |
Project DescriptionThe proposed section has the following defects: failures in both wheel paths, deep depresions, crocodile cracking and the asphalt surface is old, brittle and oxidised. Both the surface and pavement have major failures.
Pavement rehabilitation consisting in-situ stabilisation of the existing pavement and a new asphalt wearing surface (using 50mm thick size 14mm dense graded asphalt) including the installation of subsoil drainage.
Total cost of proposed project is $157,400 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2016