Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Nov 2015 - Jan 2016 |
Australian Government Contribution: | $87,604 |
Local Council/Shire: | Horsham Rural City Council |
State: | VIC |
Project DescriptionGravel shoulder is weathered due to rain, wind and heavy traffic. Sealed edge breaaking and shoulder drop-off are to be addressed.
Reshaping the shoulder both sides and topping them with 100 mm compacted thickness of gravel to provide a smooth riding shoulder surface and improved drainage. Length 2780 metres x 2 metres (both sides). |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/05/2016