Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Aug 2015 - Nov 2015 |
Australian Government Contribution: | $300,000 |
Local Council/Shire: | Lismore City Council |
State: | NSW |
Project DescriptionPavement & Surface failure defects
The works will include pavement reconstruction to improve safety, structural integrity and ride characteristics of the road
Total cost of proposed project is $345,266 |