Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Nov 2015 - Jan 2016 |
Australian Government Contribution: | $750,000 |
Local Council/Shire: | Ballarat City Council |
State: | VIC |
Project DescriptionUrban collector road lost shape and pot holing badly in large residential area
Pavement reconstruction, kerb and channel, underground drainage works, line marking and associated works.
Total cost of proposed project is $822,000 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/02/2016