Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Oct 2015 - Nov 2015 |
Australian Government Contribution: | $111,955 |
Local Council/Shire: | Shire of Merredin |
State: | WA |
Project DescriptionCracking and rutting of road surface, and broken and crack kerbing and drainage.
Asphalt seal whole road. Remove broken kerbing and replace with mountable kerbing. Remove damaged drainage grates and replace with side entry pits. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/02/2016