Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Oct 2015 - Jun 2016 |
Australian Government Contribution: | $276,000 |
Local Council/Shire: | Coomalie Community Government Council |
State: | NT |
Project DescriptionArea of bitumen seal and pavement have failed.
Removal of 10,000 square metres of bitumen seal and substandard gravel pavement, incorporation of cement into existing pavement, provision of additional gravel, shape and compact.
Lay initial slurry bitumen seal and lay final bitumen seal and 14 millimetre aggregate.
Total cost of proposed project is $564,886 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/08/2016