Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Oct 2015 - Jan 2016 |
Australian Government Contribution: | $472,972 |
Local Council/Shire: | Brimbank City Council |
State: | VIC |
Project DescriptionThe existing road pavement is ageing and exhibits oxidation and areas of significant longitudinal and crocodile cracking, loss of aggregate and patching. There is also significant roughness.
The project includes the following major aspects:
• Rehabilitation of 514 metres of existing road pavement and resurfacing with asphalt
• Reconstruction of 1053 metres of existing kerb and channel
• Reconstruction of existing vehicle crossings where required
• Construction of 187 metres of underground drainage works
• Reconstruction of all footpath
• Construction of 6 raingardens
Total cost of proposed project is $699,407 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/05/2016