Project DescriptionThe road is very loose and corrugated with at least 50 % of the road area showing exposed subgrade. There are washouts, scouring due to poor and lack of drainage. This project aims to improve accessibility and safety.
Prepare existing surface by grading, heavy watering and compaction to produce 7.0m wide subgrade with 4% crossfall. Construct new gravel layer of 150mm and compacted according to standard specification to protect the formation and provide a wearing course for traffic.Two way Crossfall of 4% is required to drain the pavement. Reinstate offlet Drains and Blocks. Construct additional offlet drains and blocks. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/04/2016