Funding Program: | Roads to Recovery Program |
Status: | Completed |
Transport Mode: | Road |
Expected Start/Finish: | Mar 2018 - Mar 2019 |
Australian Government Contribution: | $162,626 |
Local Council/Shire: | Shire of Northampton |
State: | WA |
Project DescriptionRoad seal is only 3.5 metres in width at these sections and is unsafe for passing of trucks and vehicles, road is a 27.5 metre road train route and school bus route
Reconstruct section to a bitumen sealed width of 7 metres, apply one coat of bitumen using 14mm aggregate, and construct gravel shoulders on each side of bitumen to 1.2 metres wide aggregate. A second coat seal to be applied in 2017/18 |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 10/07/2019