Replacement of St Marys and Upper Scamander Bridges

Funding Program:Investment Road and Rail Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Mid 2017 - Late 2017
Estimated Project Cost:$665,000
Australian Government Contribution:$300,000
Local Council/Shire:Break O'day Council
State:TAS

Project Description

The project replaced three timber bridges in the St Marys region and one timber bridge at Upper Scamander.

Benefits

The project has improved safety, increased load capacity, improved freight efficiency and reduced maintenance costs.

Funding

The estimated cost of the project is $665,000. The Australian Government is contributing $300,000 and the Break O'Day Council $365,000.

Timetable

The project commenced construction in May 2017 and was completed in November 2017.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 28/09/2018