Funding Program: | Northern Australia Roads Program |
Status: | Under construction |
Transport Mode: | Road |
Expected Start/Finish: | Mid 2019 - Early 2021 |
Estimated Project Cost: | $28,750,000 |
Australian Government Contribution: | $23,000,000 |
Local Council/Shire: | Whitsunday Regional Council |
State: | QLD |
Project DescriptionThe Bowen Developmental Road is a rural strategic main road connecting the Bruce Highway at Bowen to the Gregory Developmental Road. The route is currently partially sealed.
The project will upgrade unsealed sections of Bowen Developmental Road between the Gregory Developmental Road (near Belyando Crossing) and Collinsville. The project comprises sealing to an 8 metre formation and drainage works. BenefitsThe project will support growing traffic volumes on the Road from a diverse range of road users, including mining and agricultural industries, local communities and tourists.
The project will provide the following benefits:
- increased road safety for passenger and freight vehicles, through the sealing of unsealed sections
- reduced vehicle operating costs, through improvements to road surfaces
- improved travel-time reliability
FundingThe Australian Government has committed up to $23 million towards this $28.75 million project. TimetableConstruction commenced in August 2019 and is expected to be completed by early 2021, weather permitting. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 14/11/2019