Department of Infrastructure, Regional Development and Cities print logo Building our Future print logo

Bloomfield Road (Rural Road) - 067691-16NSW-RTR

Funding Program:Roads to Recovery Program
Status:Under construction
Transport Mode:Road
Expected Start/Finish:Sep 2018 - Nov 2018
Australian Government Contribution:$75,000
Local Council/Shire:Cobar Shire Council
State:NSW

Project Description

Existing causeway on Sandy Creek is unformed. During wet weather this causeway can become impassable for significant periods of time.

The causeway will be formed by overlaying up to 150 mm gravel and then will be stabilised and sealed

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.