Baroma Downs Road (Rural Road) - 068813-16NSW-RTR

Funding Program:Roads to Recovery Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:May 2017 - Jun 2017
Australian Government Contribution:$91,857
Local Council/Shire:Gwydir Shire Council
State:NSW

Project Description

Several isolated failures of the pavement along a 4.6km section of the road with breaking of the sealed surface caused by water ingress and heavy vehicle use.

Heavy patching of 900 square metres in several sections. Existing base material will be stabilised with 3% by weight of 70:30 cement/flyash. The failed sections will be reshaped and recompacted then a two coat bitumen seal will be applied over the patch to seal the pavement from water ingress.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.