Outback Way - 2016 Election Commitment - QLD - Donohue Highway Progressive Sealing Package 2

Funding Program:Investment Road and Rail Program
Status:Under construction
Transport Mode:Road
Expected Start/Finish:Mid 2019 - Mid 2021
Estimated Project Cost:$10,480,000
Australian Government Contribution:$8,380,000
Local Council/Shire:Boulia Shire Council
State:QLD

Project Description

The project involves approximately 25km of sealing across multiple sections of the Donohue Highway from gravel to a two-lane seal.

Benefits

The project is expected to deliver the following benefits:

  • reduced travel time for all road users
  • reduced costs to freight operators and improved route reliability through a decrease in road closures and reduced vehicle operating costs
  • improved economic opportunities for all industries (such as mining and tourism) through improved access across the region
  • reduced accidents by improving the overall safety of the route

Funding

The Australian Government will provide 80% of the project costs capped up to a contribution of $8.38 million, subject to the Council providing 20% of the project costs.

Timetable

Construction commenced in July 2019 and is expected to be complete in mid-2021.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 25/09/2019