Outback Way - 2016 Election Commitment - QLD - Kennedy Developmental Road Pavement Widening Package 1

Funding Program:Investment Road and Rail Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Mid 2019 - Early 2020
Estimated Project Cost:$3,880,000
Australian Government Contribution:$3,100,000
Local Council/Shire:Boulia Shire Council
State:QLD

Project Description

The project involves approximately 17.13km of works to widen the existing road to a six-metre seal on an eight-metre formation.

Benefits

The project is expected to deliver the following benefits:

  • reduced travel time for all road users
  • reduced costs to freight operators and improved route reliability through a decrease in road closures and reduced vehicle operating costs
  • improved economic opportunities for all industries (such as mining and tourism) through improved access across the region
  • reduced accidents by improving the overall safety of the route

Funding

The Australian Government will provide 80% of the project costs capped up to a contribution of $3.1 million, subject to Queensland providing 20% of the project costs.

Timetable

Construction commenced in June 2019 and was completed in April 2020.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 11/05/2020