Outback Way - 2016 Election Commitment - QLD - Kennedy Developmental Road Pavement Widening Package 2

Funding Program:Investment Road and Rail Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Early 2020 - Late 2020
Estimated Project Cost:$4,820,000
Australian Government Contribution:$3,860,000
Local Council/Shire:Boulia Shire Council
State:QLD

Project Description

The project involves works to widen more than 5 kilometres of the existing road to a six or eight-metre seal, depending on the requirements of the road.

Benefits

The project is expected to deliver the following benefits:

  • reduced travel time for all road users
  • reduced costs to freight operators and improved route reliability through a decrease in road closures and reduced vehicle operating costs
  • improved economic opportunities for all industries (such as mining and tourism) through improved access across the region
  • reduced accidents by improving the overall safety of the route

Funding

The Australian Government will provide 80% of the project costs capped up to a contribution of $3.86 million, subject to Queensland providing 20% of the project costs.

Timetable

Construction commenced in April 2020 and was completed in September 2020.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 25/01/2021