Outback Way - 2016 Election Commitment - NT - Tjukaruru Road Progressive Sealing

Funding Program:Investment Road and Rail Program
Status:Completed
Transport Mode:Road
Expected Start/Finish:Late 2020 - Mid 2021
Estimated Project Cost:$19,900,000
Australian Government Contribution:$15,920,000
State:NT

Project Description

The project involves approximately 24 kilometres of upgrading across one section of Tjukaruru Road from formed road to a two-lane seal.

Benefits

The project is expected to deliver the following benefits:

  • reduced travel time for all road users
  • reduced costs to freight operators and improved route reliability through a decrease in road closures and reduced vehicle operating costs
  • improved economic opportunities for all industries (such as mining and tourism) through improved access across the region
  • reduced accidents by improving the overall safety of the route

Funding

The Australian Government will provide 80% of the project costs capped up to a contribution of $15.92 million, subject to the Northern Territory providing 20% of the project costs.

Timetable

Construction commenced on the project in late-2020 and was completed in mid 2021.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.