Funding Program: | Urban Congestion Fund |
Status: | Under construction |
Transport Mode: | Road |
Expected Start/Finish: | Early 2021 - Mid 2021 |
Estimated Project Cost: | $61,400,000 |
Australian Government Contribution: | $30,700,000 |
Local Council/Shire: | City of Mitcham |
State: | SA |
Project DescriptionThe project involves an upgrade of the existing staggered T-junction intersection at Goodwood, Springbank and Daws Road intersection. BenefitsThe project will:
- Improve safety
- Reduce congestion
- Improve travel times
FundingThe Australian Government is providing up to $30.7 million towards this project. TimetableConstruction commenced in January 2021 and was completed August 2021. |
Disclaimer: The material contained in this site is made available
on the understanding that the Department is not thereby engaged in rendering professional
advice for a particular purpose. Before relying on the material in any important
matter, users should carefully evaluate the accuracy, completeness and relevance
of the information for their purposes and should obtain appropriate professional
advice relevant to their particular circumstances.
Project details last updated: 25/03/2022