Department of Infrastructure, Transport, Cities and Regional Development print logo Building our Future print logo

Davey Road Interchange

Funding Program:Investment Road and Rail Program
Status:Under construction
Transport Mode:Road
Expected Start/Finish:Late 2020 - Early 2022
Estimated Project Cost:$16,500,000
Australian Government Contribution:$7,900,000
Local Council/Shire:Albury City Council
State:NSW

Project Description

This project involves:

  • Construction of two south facing ramps (on and off), approximate 1.6 kilometres in length, at the existing overpass of Davey Road with the Hume Highway
  • Construction of two roundabouts (one on the eastern ramp intersection, and one on the western ramp intersection)
  • Residual works

Benefits

The Project will improve safety, increase efficiency, productivity and reduce congestion.

Funding

The Australian Government contribution is capped at $7.9 million.

Timetable

Construction commenced in December 2020 and is expected to be completed by early 2022.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 8/02/2021