Newman to Katherine Corridor Upgrade (WA) - Great Northern Highway Upgrade – Ord River North Section, Stage 3

Funding Program:Roads of Strategic Importance
Status:In planning
Transport Mode:Road
Expected Start/Finish:Early 2023 - Late 2023
Estimated Project Cost:$39,000,000
Australian Government Contribution:$31,200,000
Local Council/Shire:Shire of Halls Creek
State:WA
Corridor:Perth - Darwin

Project Description

The project includes widening and overlay, reconstruction and realignment on Great Northern Highway between SLK 2937.98 to 2939.20 and SLK 2941.15 to 2950.05. Design and construction of a new Bridge No. 1260A (GNH over Frog Hollow Creek), at SLK 2946.63, including approach works and demolition and removal of the existing Bridge No. 1260.

Benefits

Benefits include:

  • Improved road safety for all road users.
  • Improved efficiency and network reliability.
  • Improved accessibility and connectivity of road networks.

Funding

The Australian Government has committed $31.2 million towards the $39.0 million project.

Timetable

Construction is expected to begin in early 2023 and be completed in late 2023.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.