Newman to Katherine Corridor Upgrade (WA) - Port Hedland Airport Deviation

Funding Program:Roads of Strategic Importance
Status:Under construction
Transport Mode:Road
Expected Start/Finish:Mid 2022 - Mid 2023
Estimated Project Cost:$76,000,000
Australian Government Contribution:$50,200,000
Local Council/Shire:Town of Port Hedland
State:WA
Corridor:Perth - Darwin

Project Description

The project will construct a 5 kilometre single carriageway to realign the Great Northern Highway away from the Airport, construct a single-span concrete road bridge over a duplicated rail line, construct two access roads and relocate a tourist information bay.

The project will improve road safety by separating heavy vehicle through traffic from the built up area. It is also expected to improve network operation efficiency by removing delays caused by the at-grade crossing with a road over bridge.

Benefits

  • Improved road safety for all road users
  • Improved efficiency and network reliability
  • Improved connectivity between people with jobs and services, and goods with market

Funding

The Australian Government has committed $50.2 million towards the $76 million project.

Timetable

The project commenced construction in August 2022 and is expected to be finished by mid 2023.

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.


Project details last updated: 5/09/2022