• Funding program Investment Road and Rail Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Early 2018 - Early 2019
  • Estimated project cost $500,000
  • Australian Government contribution $500,000
  • Local Council/Shire Burnie City Council,Waratah/Wynyard Council
  • State TAS

Project description

Complete a comprehensive road safety and traffic flow study to examine blind spots, traffic blockages and the bottleneck at the Cam River Bridge between Cooee and Wynyard.

Benefits

This planning project is expected to lead to an improvement in the efficiency and safety of transport operations on the Bass Highway.

Funding

The Australian Government is fully funding this up to $500,000 project.

Timetable

The project commenced in February 2018 and the final plan was completed in March 2019.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.