• Funding program Investment Road and Rail Program
  • Status Underway
  • Transport mode Road
  • Expected start/finish Early 2023 - Mid 2027
  • Estimated project cost $75,000,000
  • Australian Government contribution $60,000,000
  • State NT

Project description

The project will upgrade and seal sections of the access roads on the Tiwi Islands, including the Paru Road.

Benefits

By improving roads on the islands, this project will:

  • support economic growth opportunities, particularly those associated with the potential export of plantation timber;
  • create local employment opportunities; and
  • provide all-weather access to Tiwi College on Melville Island.

Funding

The Australian Government committed $60 million toward this $75 million project in partnership with the Northern Territory Government.

Timetable

Scoping and investigation activities started in January 2021. Construction is anticipated to commence in early 2023 and be completed by mid 2027.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.