• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2021 - Mar 2022
  • Estimated project cost $16,086
  • Australian Government contribution $15,029
  • Local Council/Shire Port Pirie Regional Council
  • State SA

Project description

Loss of road sealing aggregate

Reseal road with 10/5mm two coat seal

Total cost of proposed project is $16,086

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.