• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2022 - Oct 2022
  • Estimated project cost $70,000
  • Australian Government contribution $70,000
  • Local Council/Shire Douglas Shire Council
  • State QLD

Project description

Kerb and Channel failing and this affects the accesses and drainage along Mossman street. Replacing the old kerb and channel will improve drainage and parking along Mossman Street.

Remove existing kerb and channel and improve the vertical alignment to improve drainage and access to properties. Replace with new Kerb and Channel.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.