• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2013 - Feb 2014
  • Estimated project cost $1,800,000
  • Australian Government contribution $402,231
  • Local Council/Shire Manningham City Council
  • State VIC

Project description

Insufficient lane widths for current traffic volume compared to current Road Design Standards, sight distance is insufficient due to substandard road crests, there are no bicycle facilities or footpaths, open drains present a hazard to traffic and perform poorly resulting in inundation of some adjacent properties, and night time visibility is poor due to insufficient street lighting.

Pavement rehabilitation, pavement widening, underground stormwater drainage construction, kerb and channel, footpath and footpath imporvements to bicycle and pedestrian facilities.

Total cost of proposed project is $1,800,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.