• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2013 - Oct 2013
  • Estimated project cost $352,997
  • Australian Government contribution $352,997
  • Local Council/Shire Temora Shire Council
  • State NSW

Project description

This section of Trungley Hall road is rough and has a narrow sealed pavement of 5 metres, which does not allow for safe overtaking or passing.

To import 150mm of pavement material and widen sealed pavement to 6.8 metres. The work also including the widening of 12 culverts along this section of road to to 9 metres in length

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.