• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2013 - Feb 2014
  • Estimated project cost $74,713
  • Australian Government contribution $66,957
  • Local Council/Shire Shire of Kulin
  • State WA

Project description

Poor horizontal alignment, gravel base has deteriorated leaving road slippery and dangerous when wet.

Widen existing road running surface, reconstruct and gravel for 5km to a width of 11m with 9m running surface

Total cost of proposed project is $74,713

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.